After having to put astronomy on hold for over 2 years due to dealing with a divorce and moving houses because of that, I finally got started with getting back into astrophotography again. Sadly, I had to abandon my balcony observatory (LOMO) as well, and with it that also my great views.

 

This first post will show a summary of my build progress that took place between April 18 and May 27 2020.

1164907784_Bruintingerbrink_stitchAnno.thumb.jpg.3ebd856482a6c53868f03916b548593d.jpg

My new place doesn't have the best of views, but we will just play with what we have. (sorry about Dutch annotation).

 

IMG_1328.JPG.ac98aedaa6a3c277f54ddfc546ecf1b2.JPG

View of the backyard before construction started, the obsy will be build on the right side in the picture, as this will give me the most clear views around.

 

IMG_1422.JPG.1b74cedf57ad7f9132c8d06b4d6da4da.JPG

Cleared the vegetation and removed the artificial grass.

 

IMG_1426.JPG.7937b4ab329bdcdca42625274219fa98.JPG

Outlined the dimensions, and preparation for pouring the concrete pier foundation.

 

IMG_1431.JPG.2a89bd5da9e43fc953746700f6fc8dd5.JPG

Trying to strike Oil........ but with the low Oil prices due to Covid pandemic, I decided to just use the hole for the pier foundation anyways.

 

IMG_1433.JPG.65cef6d329f951e7b93f4bf885f0486e.JPG

Ready for pouring concrete, hole is 50x50 cm and about 75 cm deep.

 

IMG_1436.JPG.2d2bfacb10d0e02583f6da0e479e836f.JPG

Almost 400 kg of concrete later.......

 

IMG_1439.JPG.fa3452e4e6702b4d070f676c029fa0ee.JPG

Waiting for concrete to settle during the week.

 

IMG_1442.JPG.d6cee30dd6504b4794fa9cddebae1b13.JPG

Adapters to hold the floor frame. Frame will be placed on 12 of these.

 

IMG_1443.JPG.06c39b47bbf6a12f1a3c23bd3775d658.JPG

Floor frame.

 

IMG_1444.JPG.9cc2eb5e08d4f161eb07997eddb9e42a.JPG

Lots of wood in a small shed........

 

IMG_1445.JPG.3220bf47460548e96b8040683ec27ae0.JPG

Floor frame concreted in place.

 

IMG_1446.JPG.fccff4aa76298f5e524a2f89b2a98acb.JPG

Wall frames placed.

 

IMG_1450.JPG.19b6cf33b05bc41f837967a0f60899d3.JPG

Roll off roof frame placed.

 

IMG_1451.JPG.d5706f0bd6e793c5ca1c6b83e5ec48a7.JPG

Lock down installed (and not for Covid in this case).

 

IMG_1452.JPG.2642e5046f4f731bdc98b259ed85e552.JPG

Damp open membrane placed.

 

IMG_1453.JPG.abbfe0a219f8347e43e71e5e7db07e9d.JPG

Shiplap applied to South/West/North walls.

 

IMG_1456.JPG.30f5001dd690aac524f1d80aa7758ef5.JPG

Door crafted and shiplap applied to East wall.

 

IMG_1457.JPG.cb21ff8209b03820b52f684491b9f969.JPG

Roof plated and shiplap applied.

 

IMG_1460.JPG.bef0980352f30970798ea3c481a6ccbb.JPGIMG_1461.JPG.12e41bd735c160d32baf6b2b04a23f74.JPG

Guttering and roof trim applied.

 

IMG_1462.JPG.c1744ceaf876301523c4bcce5b752ce3.JPG

Finished underside.

 

IMG_1465.JPG.751e2fc7a53a3b4e618aa0a4269c033b.JPG

Electrical/Data cable preparation.

 

IMG_1466.JPG.1eba2b85d6159a17f31e17f85ec0af4c.JPG

OSB flooring.

 

IMG_1468.JPG.6995aed6778fb6132ebeb76bf657d8bd.JPGIMG_1470.JPG.2204b7379e783673e36ce589959f312e.JPG

Wall insulation, finished with meranti plywood (kinda looks a bit like storm clouds on Jupiter). Aluminium profile to hold LED lighting strip.

 

IMG_1471.JPG.fc03f5f727978f72ba74d313b64b73d4.JPG

Finishing touches to wall top sides.

 

IMG_1473.JPG.01b60020c01ea719481d09b5c970ff3b.JPG

First piece of kit to go in; PC monitors on the wall.

 

IMG_1474.JPG.3b1f7a6cbf5d65f71261e9c2f5291a25.JPG

Added some pipe insulation to act as wind barrier on the roof trim.

 

 

Edited by Astrovirus2
  • Like 13
Link to comment
Share on other sites

Did a lot of work, together with my dad, on getting the power and data connections installed. Not completely done, but all cables are in placed, mains ready for connecting to sockets when they are installed in the obsy, data cable in place in the conduit as well.

IMG_1475.JPG.e66844941cee0a9f02de8215705be6b2.JPG

Data cable originating from router on the other side of the wall. Also shows mains splitting from power of my house shed.

 

IMG_1476.JPG.0a86798f04875163105805fddc3c959e.JPG

Added additonal spare socket to the shed as well, and installed ethernet switch for connecting to the obsy. Main power supply going towards obsy going out at the bottom.

 

IMG_1477.JPG.a30000cd0867256583756eaccc4b316a.JPG

Mains and data connection runnig thru the 2 inch conduit (15 m) towards obsy.

 

IMG_1478.JPG.380c69c19fc11edd1dd1399dd2d6d812.JPG

After 15 m, the conduit goes underground for another 6-7 m to surface next to the pilar.

 

IMG_1479.JPG.d0795a2069525336c73692b4c693f24e.JPG

Also started work on the a partly removable raised floor for visual observing (and more easy maintenance as well), half of this florr will be permanent, the other half will be removable, and only be put into place when needed.

Edited by Astrovirus2
  • Like 1
Link to comment
Share on other sites

Another joyfull day of working under sunny skies on the Obsy.

IMG_1482.JPG.c0b5f569e3cb37d70823718d763fed88.JPG

Finished the frame for the raised floor, half of which will be fixed, and the other half will be removable. The frame will serve for visual observing and more easy acces to the equipment for maintenance and adjustments.

IMG_1483.JPG.b7e074078572c42156231ed7a00e76e6.JPG

Little stair case to raised floor.

IMG_1484.JPG.1ad03867f66971d802e696db88db8e21.JPG

Also received a new piece of kit today, so sorry for the clouds.

 

 

  • Like 9
Link to comment
Share on other sites

Got myself some steel to have en nice pier farbicated soon hopefully.

IMG_1490.JPG.505152928165207ed84a6b7b344e3db3.JPG

160x160 mm, 6mm thick main pilar, 1.6 meters long

 

IMG_1489.JPG.ccf0808595a7adc4b415000f6ff4c144.JPG

400x400 mm 15 mm thick foot plate, 250x250 mm 10 mm thick top plate to hold the brake disk NEQ adapter from my old obsy, and finally 80x800 mm, 5 mm thick stabilizing fins (x4)

 

  • Like 1
Link to comment
Share on other sites

You are absolutely right Andrew, I just realised this potential issue recently, and had not thought that it may pose an issue on damp nights, when condesation could occur on the roof, which could then end up in the observatory. It has however a gutter installed already, which moves with the roof opening. However, a small design flaw is, that I should have made it wider so it drains besides the wall. I will probably circumvent the potential issue that this may cause on damp nights, by plugging/unplugging the draining hole when I open/close the roof.

 

Edited by Astrovirus2
Link to comment
Share on other sites

I actually decided to completely redo the gutthering, to correct the design flaw. It actually drains on the side of the observatory, so when the roof is opened, there is no risk of condesation from the roof ending up in the observatory.

IMG_1492.JPG.cffd28fd1fd4507327763e71b80ac266.JPG

IMG_1493.JPG.06fc164f6db7e5bf8f3c7e156c012de8.JPG

IMG_1494.JPG.1aa5b764d2e77dfbc7647db0d9d09623.JPG

  • Like 2
Link to comment
Share on other sites

  • 2 weeks later...

Lots of small things to work on currently.

IMG_1496.JPG.c67466fe3223e7c54e8550456d54c404.JPG

North pier side console, holding 2 sockets and a main power switch to disconnect all equipment from mains.

IMG_1497.JPG.e0bcbe6b481d1fbd7120bf15c882f762.JPG

South pier side console, holding the control PC

IMG_1500.JPG.f9698a99f10332430a262e70f7a7c69b.JPGIMG_1501.JPG.ea2bfcf4c4d6c187556a37964301e19f.JPG

Roof insulated and finished with some 3 mm ply wood.

IMG_1504.JPG.9e9be39da4ac30852d7ae8bae4b3d749.JPG

Remaining opnings at the front of the roof closed off with brushes.

IMG_1507.JPG.41df22e0436da7544c86686f01abfb2b.JPGIMG_1510.JPG.b085ca645f22b5a3ce0b0d0e1b346d3d.JPG

Same at the back end.

IMG_1506.JPG.509cd96aab23043df96c3e95e2eb2d2b.JPG

Added an additional layer of aluminium to raise the wheels by about 2 mm to resolve an issue with the side of the L-profile cutting into the rollers at some spots.

 

  • Like 1
Link to comment
Share on other sites

And then there was power and light.

IMG_1513.JPG.be20dd16b6cf8437ec5b5550e3b6efde.JPG

3x 2 powersockets installed and hooked up to mains, further distribution will be done by extention leads.

 

IMG_1511.JPG.39758cd80c2a4f4a34b25c5c7afd0879.JPG

Bright white.

 

IMG_1515.JPG.499f4fe95977cd4c945c30366d53dee4.JPG

Bright red. Sadly a single red LED in the 2nd strip is defect.

 

IMG_1514.JPG.484230b83dc200c84a03a627690a2f52.JPG

Dim red.

 

Now if only the neighbors won't start getting weird ideas what's going on when the red light is on in the obsy at night........;-)

Edited by Astrovirus2
  • Like 1
Link to comment
Share on other sites

  • 3 weeks later...

First light is another step closer. The pier has been mounted, power sockets mounted, and the NEQ6 is put into place. Next will be mounting of the control PC and optics and wiring everything up.

 

IMG_1533.JPG.b1f9d0668564527d48f9ab8bcfa07814.JPG

IMG_1534.JPG.864c108c16c6ce3fa0e6b3d0c35951d0.JPG

  • Like 4
Link to comment
Share on other sites

Some more progres today.

 

IMG_1537.JPG.671779ace9ee6ec4a78336d3b145358d.JPG

I finished off the console sides.

IMG_1538.JPG.014708dd192a436061518bb5e81b2dd3.JPG

Made a place to put up the 2 DC PSU.

IMG_1536.JPG.51ef7547393ce36031bbc86920949523.JPG

And mounted to OTA and control PC to see if the OTA clears everything as expected. As a bonus, it seems the most annoying streetlight has its direct path into the OTA fully blocked by the Southern wall and roof, even at the lowest viewing angle.

  • Like 2
Link to comment
Share on other sites

  • 2 weeks later...

First light approaches..........

All equipment is placed and hooked up to power and data cables.

IMG_1543.JPG.a57dbb18d438db95fe25f0d96a7994a1.JPG

Cable management, nice and tidy. Biggest challenge was placing the PSU for the Hypercam, which is VELCROed to the back end of the OTA dove tail.

 

IMG_1545.JPG.e0d8edfd84e8e487aa09a0af5370a37c.JPG

Mission control, although on most nights this will be monitored from inside my warm house.

 

IMG_1546.JPG.ea108d0b9423fb9ea94d2c8d1c4e3cf9.JPG

Back side of the center console with mains suply.

 

Daylight testing; Slewing to Regulus.

 

Custom parking for roof clearance when closing the Observatory.

 

SGL Arduino focuser installed and up and running again.

Link to comment
Share on other sites

  • 2 months later...

OK the first serious testing has commenced, trying to get familiar with my old and new kit and also with processing astro imaging data. This image was shot on 4 clear nights between Septemebr 19th and 23rd and consists of almost 18.5 hours of data (369x 3 min, -10°Cm gain 5.62, offset 25) shot with the AA Hypercam 269C Pro TEC, calibrated with 50 darks, 21 flats and 50 bias frames and stacked in DSS, postprocessed in PI. Still need to relearn a lot in PI, but for now I am happy with my first image in about 5 years time. Also, this test shows there is quite a lot possible even under my Bortle 5-6 skies.

VdB141_2020.jpg.31446788f24bba692d8bc2ab622996ec.jpg

  • Like 4
Link to comment
Share on other sites

Hi,

Great job! - a couple of tips from experience.

1) keep one of those cheap plastic sheets that are used for decorating in the obsy, just in case it rains and something goes wrong with the roof. Then at least you can throw it over the scope or whatever. Consider it the rain equivalent of a fire blanket. Hopefully you will never need it.

2) my roll-off roof (the one in the photo) blew off in a storm (good thing I had the sheet). I had tie downs but they didn't hold (but it was a very strong storm). Why not add some reserve lock-down devices ? I use four pretty heavyweight "turnbuckles" (spanschroefen ?), which I fit if the weather is going to be bad. They are a lot less expensive than a new roof!

regards, Peter

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue. By using this site, you agree to our Terms of Use.