  1. A second way to do things is to put the plastic pipe all the way to the bottom of the hole you have dug BUT after making several large holes in the wall of the pipe below ground level - thus when the concrete is poured the concrete can freely flow between the inside and outside of the pipe and will set "holding" the pipe in place.

    Hello Rich. How Bizibilder advised above is how i did mine.

    I`ve put up a few pics to show how i did it. I hope they are of help to you. I used 160mm HPPE high pressure water pipe for the pier.

    1st pic shows all the reinforcing in place.

    2nd shows pipe in place with holes drilled at the bottom. Only one is visible in this pic but there were three at the time. I actually put four more in.

    3rd shows pipe and bracing.

    4th shows finished pier with the template with rods in place lined up north.

    post-17420-133877623708_thumb.jpg

    post-17420-133877623717_thumb.jpg

    post-17420-133877623725_thumb.jpg

    post-17420-133877623734_thumb.jpg

×
×